Make the assumptions explicit. Change the inputs and see the result.
Editable planning assumptions, not exact in-game values. Machine width and speed are prefilled where verified. Use one currency throughout.
Using GESSNER Single Row Billet Planter
CALCULATED ESTIMATE
11.44 hours
Estimated total time0.9 ha/h
Effective work capacityCapacity = width × speed ÷ 10 × efficiency. Duration = area ÷ capacity + extra minutes ÷ 60.
Use this duration in the contract planner ↗